Current/field control of the PS-Booster main magnets power converters

The PSB main magnets are powered by 28 power converters following the schematic represented in Figure 1. The fact that all circuits are magnetically coupled makes the control of these power converters very difficult, as any modification of one control loop has an effect on all the other circuits. This is particularly true for the Main Power Supplies (BR14.RMPS and BR23.RMPS), two 3000V 6000A power converters which generate high voltages that are coupled to all other power converters on rings 1 and 4 and rings 2 and 3 respectively, as disturbances in their respective control loops.

Figure 1: PSB main magnets and power converters

As an example, the voltage generated by one of the MPS during a 2 GeV Cycle is shown in Figure 2 as well as the influence that this has on the control scheme of the BDLs. The BDL power converters (powering the auxiliary windings of the dipole magnets) will see the voltage waveform shown in the same figure as a perturbation. As a consequence, the BDLs current controller was tuned primarily to attenuate the perturbation induced by the MPS and its performance was not optimal for this reason.

Figure 2: Reference generated by the MPS and voltage induced on the BDL

In addition, while it is normal for SY-EPC controllers to guarantee an accuracy of a few tens of parts per million (ppm) or less during the current ramps or the flat-tops, the peculiar injection scheme in the Booster requires it even during the transition between the two (see Figure 3).
In order to achieve the 80 ppm of accuracy on the peak to peak error in the magnetic field (Berr < 0.1mT peak to peak), even during the transients at the start and end of the ramp up, decoupling of the magnetic circuit was essential.

Figure 3: B-error at injection

This could be achieved thanks to the existing FGC Ethernet infrastructure (Figure 4). Using the inter-FGC communication channel was crucial to transmit the voltage reference of the MPS (Vref) to the power converter controllers of all the coupled circuits. The advantage of using the Vref instead of the measured voltage is that Vref is several milliseconds in advance of the measurement, giving the time to send the Vref value and to make some numerical manipulation with a digital filter (Figure 5) to accurately reproduce the effective perturbation seen by the coupled power converters.

 

Figure 4: FGC Ether communication

Figure 5: The Vref MPS is corrected with a numerical filter, before it is used in the Current controller 

In addition, the SY-EPC Fresco tool was used to measure the frequency response of the converters and loads and to calculate the control parameters. For most of the power converters, this approach, together with the decoupling action of the Vref MPS described above, was enough to achieve the requested performances.

Figure 6: Frequency identification of the MPS load

Only for the MPS, given their particularly slow controller cycle times, were additional calculations necessary. To improve the magnetic field controller we used Fresco to measure the frequency response of the converter and load for each MPS (Figure 6) and then fit a discrete transfer function to the data using Matlab. Finally this model was used to calculate a suitable controller that eventually brought us to the final desired performances (Figure 7).

Figure 7: Berror at injection after control improvement

More than four months were needed for controller optimisation of the PS-Booster power converters. The PSB operators can now benefit from a much more precise control of the magnet fields, enabling more precise control of the accelerator tune and other vital beam parameters.

Reporting from Fulvio Boattini